Friday, August 14, 2009

Word From Our Contractor







Everyone, we installed one stick of pipe yesterday, completed 4 services and one Blow Off (B/O), as we suspected the end of 309th was like a bowl of spaghetti. We had telephone lines, buried power lines and water services to contend with, but the guy's did a great job and did not break anything so no time was lost doing repairs.

We should make better progress today as we move towards 268th, there is a lot of stuff in the ground along 309th but once we turn the corner onto 268th it should open up nicely. We have locates along 309th and 268th so we hope to avoid most breaks, although they do not pick up everything.

I spoke with several neighbors and they are happy to see construction start. I'll try to give a daily update of our progress as time allows.

More to come.

Randy