Wednesday, January 27, 2010

Things are Working Now!!!

Hi all!
Just in case you didn't notice, the power went out a couple of weeks ago and the generator kicked in all by itself. It works! Also, we have disconnected our old system and we are up with the new! Yea!!~ It has been a long haul. Currently we are monitoring the new system and will do so for a few month before we move to a metered system of billing.
Now, we are getting all the information into the DOH so they will lift our boil water advisory. I met with Dereck the engineer at DOH at Cristalina last week, and he was going to give us a list of small items we need finish up in order to do the official removal of the order. Thank you for your patience, it has been a long haul!
Maria

Wednesday, January 13, 2010

Waterline update, tie it in!


Here are a few pictures of the tie in today just prior to sanding and backfill. Everything is set to do the tie in on 309th tomorrow with the 6", then there are only 13 services to hook up , grade and detail the roads and we'll be complete.

Friday, January 8, 2010

Water Shut Off Notice

Cristalina water will be shut off during the following times to install connections and meters and tie in loose ends:

314th Avenue: Monday, January 11, 2010 between 8:00 a.m. and 2:00 p.m.

312th Avenue: Tuesday, January 12, 2010 between 8:00 a.m. and 2:00 p.m.

309th Avenue: Wednesday, January 13, 2010 between 8:00 a.m. and 2:00 p.m.

We recommend that you reserve water or purchase contained water for flushing toilets and cooking.

We are so sorry for the inconvenience! Please pass this message along to your neighbors who may not have seen our notice!

Monday, January 4, 2010

Generator Approved!

Here is the note I got from Randy the contractor today:

Maria, the generator is set up and operational, if the power goes out it should start automatically and shut down when the power comes back on.

There is some good news to start this year off with!!! I guess L and I went out there and approved it today. We are finally set up!!!